Waste Bin Changeover
Hook-lift waste bin changeover procedure.
Hook-lift waste bin changeover procedure.
1
Step 1 of 4Drive truck to bin loading unloading (red) zone. Always follow site 8km/h speed limit.
Note: Be alert as other vehicles, forklifts and pedestrians may be working in the area.
2
Step 2 of 4Slowly reverse to empty bin bay and locate bin into the bay.
Note: Truck should remain in bin loading unloading (red) zone during this process.
3
Step 3 of 4Release hook from empty bin. Drive forward then reverse to pick up full bin and attach hook.
Note: Truck should remain in bin loading unloading (red) zone during this process.
4
Step 4 of 4Pick up full bin and make sure bin is secure before leaving the site.
Note: Beware of other vehicles, forklifts and pedestrians working nearby.