Knowby
Use Case Adherence to Plan
We start by strictly verifying execution against the monthly plan.
We start by strictly verifying execution against the monthly plan.
1
Step 1 of 11
We start by strictly verifying execution against the monthly plan.
2
Step 2 of 11
We query the system for the daily adherence curve. This immediate feedback allows us to detect if the accumulated extraction aligns with the forecast, or if we are seeing a deviation that requires operational adjustment.
3
Step 3 of 11
We see it now, not at the end of the month. However, numerical data is not enough.
4
Step 4 of 11
We need spatial context. We switch to the visualizer to review the extraction sequence in the pit.
5
Step 5 of 11
In this 3D environment, the platform highlights the active operational areas.
6
Step 6 of 11
The color coding is critical. It distinguishes what was scheduled for extraction today versus the plan for upcoming shifts, ensuring we are not just moving tons, but moving the right tons.
7
Step 7 of 11
Finally, we move upstream to audit the drilling process.
8
Step 8 of 11
As we know, without drilling there is no blasting, and without blasting, the shovels starve.
9
Step 9 of 11
We overlay the planned patterns with live telemetry to verify execution progress in real-time.
10
Step 10 of 11
We identify exactly which holes are completed, which are pending, and if the color depth meets design specifications.
11
Step 11 of 11
We are not going to be able to do the same. We are going to be able to do the same.