Knowby
Install new 3-way mixing valves and actuators on heating manifold
Remove and discard EOL blending valves/actuators and replace with new components.
Remove and discard EOL blending valves/actuators and replace with new components.
1
Step 1 of 10
<p>Secondary valve check to be certain that the system has remained closed off from valve replacement work.</p>

Secondary valve check to be certain that the system has remained closed off from valve replacement work.

2
Step 2 of 10
<p>Remove platform and any other obstacles to improve work area.</p>

Remove platform and any other obstacles to improve work area.

3
Step 3 of 10
<p>Drain remaining water from the 1&quot; ball valves below each blending valve.</p>

Drain remaining water from the 1" ball valves below each blending valve.

4
Step 4 of 10
<p>Remove all nuts and bolts from the flanges on the blending valve.</p>

Remove all nuts and bolts from the flanges on the blending valve.

5
Step 5 of 10
<p>Utilize podgy bars, porta power hydraulic systems, ratchet straps etc to slide out 3-way valves.</p>

Utilize podgy bars, porta power hydraulic systems, ratchet straps etc to slide out 3-way valves.

6
Step 6 of 10
<p>Replace each of the removed blending valves with the correctly specified replacements. Utilize all necessary tools as referred to in the removal process to install each blending valve.</p>

Replace each of the removed blending valves with the correctly specified replacements. Utilize all necessary tools as referred to in the removal process to install each blending valve.

7
Step 7 of 10
<p>Ensure all nuts and bolts are correctly tensioned when installing.</p>

Ensure all nuts and bolts are correctly tensioned when installing.

8
Step 8 of 10
<p>Remove and replace all 24v actuators with new units.</p>

Remove and replace all 24v actuators with new units.

9
Step 9 of 10
<p>Test operation and calibrate with Priva if necessary.</p>

Test operation and calibrate with Priva if necessary.

10
Step 10 of 10
<p>Working in conjunction with the valve replacement work procedure, open all associated valves and bleed air out of the system. Resume operation when the reticulated system is tested and operational.</p>
<p>SECTION 2 COMPLETE!</p>

Working in conjunction with the valve replacement work procedure, open all associated valves and bleed air out of the system. Resume operation when the reticulated system is tested and operational.

SECTION 2 COMPLETE!