<p>Tools List</p>

Tools List

8
Step 8 of 21
<p>Torque Values</p>

Torque Values

9
Step 9 of 21

Place the plywood piece on top of the drawer side, line it up flush with the edges, then drill through the ply into the drawer side.

10
Step 10 of 21
<p>Next, place the plywood piece on top of the drawer side, line it up flush with the edges, and drill through the ply into the drawer side.</p>

Next, place the plywood piece on top of the drawer side, line it up flush with the edges, and drill through the ply into the drawer side.

11
Step 11 of 21

Now fit the ply to the front of the drawer and drill it.

12
Step 12 of 21

With the ply fitted, lift the false floor into the van, tilting it as you go so it clears the vehicle without scratching or damaging it. Set it down carefully in its final position.

13
Step 13 of 21
<p>Now fit the front false floor section, making sure it's aligned and sits securely.</p>

Now fit the front false floor section, making sure it's aligned and sits securely.

14
Step 14 of 21
<p>With the front section in place, position the alloy bar against the underside of the main false floor. Secure it with clamps and check that it's held firmly.</p>

With the front section in place, position the alloy bar against the underside of the main false floor. Secure it with clamps and check that it's held firmly.

15
Step 15 of 21

Now fit the side floor against the main floor, clamp them tight, and fit the alloy bar underneath to hold them together.

16
Step 16 of 21
<p>Once the main false floor is in position, fit the side floor in next to it as shown. Check that it sits flush against the main floor.</p>

Once the main false floor is in position, fit the side floor in next to it as shown. Check that it sits flush against the main floor.

17
Step 17 of 21

With both floor sections in place, screw the false floor to the drawer sides to secure it.

18
Step 18 of 21

With the false floor secured, fit the 50x50 alloy bar to the front of the van.

19
Step 19 of 21

Next, fit the J-bar to the rear of the false floor..

20
Step 20 of 21
<p>Fit the J-bar to each van door side.</p>

Fit the J-bar to each van door side.

21
Step 21 of 21
<p>Please fill out the hard copy QA sheet included with the product you got.</p><p>Once filled out, please send it back to</p><p><a target="_blank" rel="noopener noreferrer nofollow" href="mailto:charl@camcoindustries.co.nz">charl@camcoindustries.co.nz</a></p><p></p><p>If the hard copy does not arrive, please contact us.</p><p><a target="_blank" rel="noopener noreferrer nofollow" href="mailto:charl@camcoindustries.co.nz">charl@camcoindustries.co.nz</a></p><p>0800 663 500</p>

Please fill out the hard copy QA sheet included with the product you got.

Once filled out, please send it back to

charl@camcoindustries.co.nz

If the hard copy does not arrive, please contact us.

charl@camcoindustries.co.nz

0800 663 500