Preventative Maintenance Checks.

Personal Protective Equipment (PPE). Gloves and Safety Glasses. If you don’t already have a pair of gloves or safety glasses, please see the store person.

QA Sheet. You will find a QA sheet at the machine, if there is no QA sheet there, see the team leader or production. A QA sheet will need to be completed at the start, throughout and, at the end of the day.
There are no tools required.

Turn main isolater switch (power switch) On.
On the console, turn the power switch On.

Press the black Safety Reset button.
Turn the lubricant switch On.
Check Top Hat height on job ticket, If the cassette requires changing you MUST get someone who is signed off as competant to do so. Training is available consult with your Line Leader for further details.

Press the blue Single Mode button on the screen.

Add your measurements by tapping GOTO MM and quantity by tapping QTY.
![<p>Press the green Start button [it will turn yellow] to start.</p>](https://knowby.show/media/storco/knowbys/06a9c7af-5b54-4892-b64b-6d1b484eedc3/steps/e3cd2733-9b97-48d1-8afb-038ab1b30b92/6927c794-ebbc-4221-9efd-81f3aee7357b.jpg)
Press the green Start button [it will turn yellow] to start.