1
Step 1 of 9

Before installing.

  • The site is ready and there is access

  • The floor is level

  • The table position matches the plan

  • Powered jobs: check where the power feed is

2
Step 2 of 9

Unpack.

  • Check the part count against the label

  • Look for transit damage

  • Photograph any damage before starting

3
Step 3 of 9
<p>Position the columns.</p><ul><li><p>Stand each column on its glides in the position on the plan</p></li><li><p>Short skins face the table centre (and the power feed on powered jobs)</p></li><li><p>3-column tables: the centre column sits under the top join</p></li></ul><p></p>

Position the columns.

  • Stand each column on its glides in the position on the plan

  • Short skins face the table centre (and the power feed on powered jobs)

  • 3-column tables: the centre column sits under the top join

4
Step 4 of 9
<p>Lift the top on.</p><ul><li><p>Two-person lift minimum</p></li><li><p>Locate each bracket in its rebate</p></li></ul><p></p>

Lift the top on.

  • Two-person lift minimum

  • Locate each bracket in its rebate

5
Step 5 of 9
<p>Dry-join tops only.</p><ul><li><p>Place the first section, then the second</p></li><li><p>Fit the biscuits and push the sections together</p></li><li><p>Tighten the 4 bench-top connectors from underneath</p></li><li><p>Check the join is flush with no gap</p></li></ul><p></p>

Dry-join tops only.

  • Place the first section, then the second

  • Fit the biscuits and push the sections together

  • Tighten the 4 bench-top connectors from underneath

  • Check the join is flush with no gap

6
Step 6 of 9
<p>Fix the top.</p><ul><li><p>Working from underneath, fix up through each bracket into the top</p></li><li><p>2 x 25 mm black hex screws per bracket</p></li></ul><p></p>

Fix the top.

  • Working from underneath, fix up through each bracket into the top

  • 2 x 25 mm black hex screws per bracket

7
Step 7 of 9

Powered jobs only.

  • Route the cable to the supply as shown on the site plan

8
Step 8 of 9
<p>Check.</p><ul><li><p>The table is stable and level</p></li><li><p>The top is seated in every bracket rebate</p></li></ul><p></p>

Check.

  • The table is stable and level

  • The top is seated in every bracket rebate

9
Step 9 of 9
<p>Hand over.</p><ul><li><p>Clean and do a final inspection</p></li><li><p>Take photos</p></li><li><p>Get customer sign-off</p></li></ul><p></p>

Hand over.

  • Clean and do a final inspection

  • Take photos

  • Get customer sign-off